The screw feeder was placed below the silo, which provides the bulk lime supply.
The river was closed for recreation and its water banned for drinking, bathing and irrigation. Major towns downstream of the San Juan River were impacted within days, and levels of heavy metals reached hundreds of times their acceptable limits. Levels eventually were diluted enough that, by the time water passed through Lake Powell and further downstream, it was safe for all uses.
The EPA immediately took responsibility and developed a remediation plan. The agency sought an onsite water treatment plant that could be operated at the remote mine location, run all year long with minimum supervision and treat the effluent over a wide range of flow rates. The need was obviously immediate.
Alexco Environmental offered an onsite solution including a 75-ton silo and feed system to feed hydrated lime to treat 200 to 800 gallons per minute of influent. Alexco contacted Vibra Screw Inc. of Totowa, New Jersey, for expertise on equipment for handling bulk powders to see what was needed and what could be shipped within a week. The company offered a volumetric screw feeder with variable speed drive and a controller with 4-20 mA remote speed input, which would allow the lime feed to automatically adjust to the changing pH of the influent. The higher the acidity, the more lime was continuously fed. The system would also treat the heavy metals.
The screw feeder was placed below the silo, which provides the bulk lime supply. Feeder discharge is to the influent feed line. Treatment includes all flow from the mine as well as water stored in the retention ponds.
The feeder uses a patented, controlled-vibration design to ensure even filling of its feed screw with uniformly dense material. This provides for extremely high feed accuracies. The feeder was molded from high-strength composite materials that provide a high degree of corrosion resistance.
The system was up and running within weeks. It operates around the clock, even through the tough Colorado winter. A large supply of lime is maintained at the site since access is difficult. Water continues to flow from the mine at approximately 550 gallons per minute. Without the treatment plant, many settling ponds would have been required.
EPA has spent more than $14 million so far in its response to the Gold King Mine spill. Water is successfully being treated, and EPA is pleased with the plant’s performance and is considering systems at other mine locations.